Will there be additional public meetings or tours of the recommended water tower sites?

Through a process of town halls and community discussion, the Village is learning a lot from the community while building a growing culture of partnership with residents of our community. The Village held three Town Hall meetings on March 13, April 15, and May 15 to educate the community on the state of water works and were able obtain feedback from the community. The Village continues to invite public feedback, please do not hesitate to contact the Village if you would like to schedule a small group or 1-on-1 meetings. Arrangements can be made to tour any of the feasible water tower sites. The Village would like to have stakeholder meetings with the groups most impacted by the recommended water tower locations.

Village Next Steps for Water Tower

Village Advisory Committee compiles public feedback and assessment for Council review May – June 2025
Staff completes site assessments & pursues additional documentation as requested by Council June – July 2025
Staff reviews findings and communicates results July – August 2025
Council reviews comprehensive analysis of all findings August / September 2025
Council communicates and holds water tower related meetings September / November 2025

 

Village Next Steps for PFAS Removal

Village Advisory Committee compiles public feedback and assessment for Council review May – June 2025
GAC media testing, General Plan prepared for OEPA review May – October 2025
Facility engineering design and OEPA review per current mandate 2026
Facility construction, brought online and operational March 2027 – March 2029
Continually monitor federal legislative and regulation changes related to the PFAS mandate Continuous

 