Through a process of town halls and community discussion, the Village is learning a lot from the community while building a growing culture of partnership with residents of our community. The Village held three Town Hall meetings on March 13, April 15, and May 15 to educate the community on the state of water works and were able obtain feedback from the community. The Village continues to invite public feedback, please do not hesitate to contact the Village if you would like to schedule a small group or 1-on-1 meetings. Arrangements can be made to tour any of the feasible water tower sites. The Village would like to have stakeholder meetings with the groups most impacted by the recommended water tower locations.
Village Next Steps for Water Tower
Village Advisory Committee compiles public feedback and assessment for Council review | May β June 2025 |
Staff completes site assessments & pursues additional documentation as requested by Council | June β July 2025 |
Staff reviews findings and communicates results | July β August 2025 |
Council reviews comprehensive analysis of all findings | August / September 2025 |
Council communicates and holds water tower related meetings | September / November 2025 |
Village Next Steps for PFAS Removal
Village Advisory Committee compiles public feedback and assessment for Council review | May β June 2025 |
GAC media testing, General Plan prepared for OEPA review | May β October 2025 |
Facility engineering design and OEPA review per current mandate | 2026 |
Facility construction, brought online and operational | March 2027 β March 2029 |
Continually monitor federal legislative and regulation changes related to the PFAS mandate | Continuous |