Is it necessary to build both the water tower and a PFAS removal facility?

Building both a new water tower and a PFAS removal facility is heavily based on the three outlined business options within the presentation.

Option 1

Continued IH water treatment and IH water distribution β€” would require both a water tower and PFAS removal facility.

Option 2

Purchase water from Greater Cincinnati Water Works (GCWW) and retain IH water distribution β€” would require only a water tower. Costly water plant demolition and well abandonments would be required as well.

Option 3

Purchase water and water distribution from Greater Cincinnati Water Works (GCWW) β€” will still require a tower. Costly water plant demolition and well abandonments would be required as well. (Option 3 was previously dismissed by Council)