U.S. flag This is the official website of The Village of Indian Hill. Here's how you know.
U.S. flag
This is the official website of The Village of Indian Hill.
Here's how you know.

Construction Projects

The Village of Indian Hill has several projects happening to improve our public infrastructure.  Visit this page often to keep up to date on major milestone accomplishments as well as notifications about construction impacts to traffic.

Road Closures Map

Click here to view an interactive map with current road closures.

Annual Street Resurfacing Program

John R. Jurgensen Co. was awarded a contract in the amount of $1,507,206.30.  They began roadway base repairs, saw cutting and removing curbs in mid-April, 2024.  Following the completion of curb replacements and base repairs, the roads will be milled and repaved.  The project is anticipated to be complete by July 2024, weather dependent.  The streets currently slated to be repaved include: Blome Rd. (Kugler Mill Rd. to Camargo Rd. as well as Spooky Hollow Rd. to the bridge), Camargo Rd. (the western Corp. line to Loveland-Madeira Rd.), Cooper Rd. (from the Corp. line to Main Street, Montgomery), Deer Crossing (Ravenswalk Ln. to the terminus), Given Rd. (Shawnee Run Rd. to Spooky Hollow Rd.), Manor Hill Ln. (Blome Rd. to the terminus), and Spooky Hollow Rd. (the western Corp. line to Blome Rd. as well as Loveland-Madeira Rd. to Given Rd.).  The road paving list is subject to change.  Lane closures will be necessary at times and will have two-way traffic maintained by flaggers, but long delays should be expected.

Camargo Culvert Replacement Project

The project is located approximately 150’ east of the Kugler Mill Rd. intersection on Camargo Rd.  The scope of work includes replacement of approximately 85’ of deteriorated pipe and two headwalls, installation of a manhole and two new catch basins, as well as installation of step pools in a steep section of the roadside ditch leading to the upstream end of the culvert.  The project was designed by Choice One Engineering, advertised and bid in May 2024.  Construction is anticipated to start in June and be complete in October 2024.  Dates of the temporary road closure will be posted when scheduled.

Drake Road Landslide Repair

On January 16, 2024 Indian Hill Water Works (IHWW) personnel responded to a water main break on Drake Road between Tangle Ridge Lane and Arapaho Lane.  The water main break saturated the soil in the hillside, resulting in the loss of a utility pole and the embankment.  The water main was repaired by IHWW.  In an effort to protect the remaining road and utilities in the area, JTM Smith was hired to address an emergency repair of the affected area for $99,600.  Their work included installation of a retaining wall and restoration of the embankment, guardrail, and pavement along the length of the slide.  The project was completed in late February, 2024.

Given Road Evaluation Maintenance

JTM Smith Construction anticipates beginning the pier wall project in late May, weather dependent.  The $49,200 project includes installation of piers in gaps along the existing pier wall (at locations of dead trees) southeast of Redbird Hollow Ln.  Dates of temporary road closures will be posted when scheduled.

Kugler Mill Culvert Rehabilitation Project

The project is located approximately 0.60 miles west of the Camp Rd. intersection on Kugler Mill Rd.  Work will be broken into two phases.  The first phase will include site improvements that consist of: inlet end headwall and wingwall modifications, grading, rip-rap installation, and minor pavement repair. The scope of work in phase two includes the interior rehabilitation of a 103 ft. long, 7’-9” x 7’-0” cast-in-place reinforced concrete box culvert.  The culvert projects on Kugler Mill are being designed by Choice One Engineering.  The project is expected to be advertised and bid in early summer.  Construction completion is anticipated in early 2025.  Dates of temporary road closures will be posted when scheduled.

Miami Road Water Main Replacement

Evans CivilPro is finalizing the construction plans to have the project ready to advertise in 2025.  The project is located along Miami Road between Indian Hill Rd. to Rock Hill Ln.  Two-way traffic is anticipated to be maintained by use of flaggers.

Public Works Facility Improvements

A bid opening was held to replace the fence surrounding the Public Works complex on March 21, 2024.  Burcor Fencing was awarded the project contract.  The contract cost is $155,787, which is less than the Village’s budget of $180,000.  The fence installation should be complete by the end of May 2024.  Half of the rear garage addition on the premises will also be re-roofed later this year.  Wm. Kramer & Son, Inc. was awarded the roofing project contract for a base bid of $373,990, which is less than the Village’s budget of $400,000.

Stephan Field Improvements

The $235,871 playground replacement was completed in 2023.  Indian Hill Public Works staff removed the existing retaining wall and a contractor reinstalled the wall for $25,000, at a location further away from the existing tennis courts.  Roof repairs on the existing picnic shelter will begin this spring and are expected to be complete by July.  New pickleball courts will be added this fall.

Sycamore Creek Restoration & Habitat Enhancement

The Village of Indian Hill was awarded $1,410,000 in Water Resource Restoration Sponsor Program (WRRSP) funding from the Ohio EPA to restore a portion of Sycamore Creek as well as perform reforestation, invasives removal, and habitat enhancement in the vicinity. The project limits are on Village-owned property along Loveland Madeira Road from approximately Spooky Hollow Road to Sleepy Hollow Road. Beaver Creek Hydrology, the environmental engineering consultant, is finalizing the design drawings. Beaver Creek is in the process of obtaining all necessary permits for the work with both the Army Corps of Engineers and the Ohio Environmental Protection Agency. Stream Restoration Specialists performed the required tree clearing work in late March 2024. This was done in effort to keep the project on schedule as there are permit restrictions on tree clearing April 1 – September 30 due to potential impacts with endangered species (i.e. Indiana bat). The clearing is necessary to facilitate re-establishment of the approximately 40-foot-wide stream channel and surrounding floodplain bench and addition of proposed wetland areas. Nearly all of the removed trees will be utilized in the project for toe-wood and log structures. Once all permits have been approved this spring, the design plans will be finalized, and the remaining construction activities will follow. The project is scheduled to be completed in November 2024.

Sign Up Below For Email Updates 

With a population of around 6,087 people, it is technically a city but its life style over the years has remained constant, that of a quiet residential community. Indian Hill is located in Hamilton County, Ohio, just a few miles northeast of the City of Cincinnati.

Contact Us

6525 Drake Rd,
Cincinnati, OH 45243
(513) 561 - 6500

Copyright © Village of Indian Hill. All rights reserved.