Annual Street Resurfacing Program
The budget for the 2025 road program is $1,200,000. The Village’s funding application to Hamilton County requesting $66,300 of Municipal Road Funds (MRF) was successful. This brings the total project budget to $1,266,300. The project was awarded to John R. Jurgensen. Street paving list is as follows:
Muchmore Road
Muchmore Point
Crabtree Lane
Sentinel Ridge
Camp Road – South end
Kugler Mill – East end
Given Road – Trail head south to corporation line
Spooky Hollow Road – top of hill to Blome Rd.
Hopewell Road – Weil Rd. to East corporation line
Algonquin Drive
Camp Dennison Park parking lot
The project began in May. Paving has been complete and pavement markings are nearing completion. Temporary lane closures, and possibly limited road closures, are anticipated on roadways during construction.